Assemble/Fuse Loops Then Put Into Trenches

Discussion in 'Geothermal Loops' started by mntnvew, Sep 25, 2022.

  1. mntnvew

    mntnvew New Member

    Seven “down-and-back” loops, 600’ long, 10-11’ deep.

    No one is getting into any of these for obvious safety reasons.

    Does assembling and fusing the 3/4” into my 7-loop manifold above ground and then putting it into the trenches sound like a plausible idea? The supply and return will be roughly 140’ each way of 2”.

    The other option is digging a much wider spot for the manifold and make it stepped so it is safe to get into but that is MORE digging!

    Appreciate input!
     
    Last edited: Sep 25, 2022

Share This Page