Bringing this back up again, the last two summer have been mild here, not many 90 degree days, which is when this unit struggles to keep up. We...
Sorry for the delay and thanks for asking, unit is still underperforming when the temperatures are 90+ outside. I asked the contractor to ask the...
New duck work in the attic installed by the contractor to bring up to code. Attic is insulated with R-30 Water Furnace, I am still looking for...
WF, I did not recieve a copy of the blower door test. Even if I had, I feel this should have been taken into account with the initial load...
Update I have seen no savings at all during the winter, this unit is actually way more expensive than my 1994 luxaire heat pumt. It does do...
I asked the contractor what else needs to be sealed, he said he did not know, just get up in the attic and look. How do we know there is still a...
Sorry for the confusion, there is one trench 300' that both loops lay in. close together. The ditch witch loop goes out 250 some feet then makes...
Three pipes. two 600' loops (300' long trench) laying side by side in the bottom of a trench, one that was added later that was approx 500'...
total linear feet on the loop is 1200+260=1460' I can only go by what the contractor said, he said flow was 8-11 per minute Can I put a gage...
Joe Thanks for the reply and advice. Please move to North Carolina. The 30 gallons was after the additional loop was added. It may have been...
I did not get a loop design. 2 loops, both are side by side in the bottom of the trench. This came up earlier in this post, if there are...
Here is the info I have, if you need more just tell me what to request. The loops were installed (1200', 4 300' loops) in one trench at approx...
I will get my wife to scan the documents I have. If they are not what we need to review, I can ask the contractor for more. Here are some...
update..... Hello Everyone, Just wanted to provide an update on my situation in hopes you can help me find a solution. After the new loop...
Joe, Thanks for the reply, exactly the type of feedback I am looking for. Is the heat gain a number the contractor can give me? Added loop...